William Byrd High School
William Byrd High School was built in 1969 and currently houses 1,150 students and 125 staff and administration. Having been through several addition and renovation projects, this is the most extensive project yet, covering the vast majority of the school.
This 4-phase project is spread across the school’s first and second floors and entails over 100,000 square feet of renovations and roughly 16,800 square feet of additions. Renovations include Science Labs, Band Room, Weight Room, Media Center, Guidance, Library, and Front Lobby. Additions include Choir and Art rooms, Wrestling & Cheer, a front entrance portico, and new toilets at the cafeteria. Preliminary work included building assessments of existing conditions and fire and life safety features.
K-12 EDUCATION